A contractor employed 210 men to build a house in 60 days.After 12 days, He was joined by 70 more men.In how many days will the remaining work be finished?

Asked by Suraj Wangate(student), on 5/10/12

Answers

X = 36 DAYS

Posted by Ash Naaz(student), on 5/10/12
EXPERT ANSWER

Here is the link for the answer to your query.

 

http://www.meritnation.com/discuss/question/1983808/0/

Posted by Aakash Sharma(MeritNation Expert), on 9/10/12

This conversation is already closed by Expert