A contractor employed 210 men to build a house in 60 days.After 12 days, He was joined by 70 more men.In how many days will the remaining work be finished?

EXPERT ANSWER

Aakash Sharma ,Meritnation Expert added an answer
Answered on 9/10/12

Here is the link for the answer to your query.

 

http://www.meritnation.com/discuss/question/1983808/0/

This conversation is already closed by Expert

View More
Ash Naaz , From Al Mawarid International School , added an answer
Answered on 5/10/12

X = 36 DAYS