A contractor employed 210 men to build a house in 60 days.After 12 days, He was joined by 70 more men.In how many days will the remaining work be finished?

Here is the link for the answer to your query.

 

https://www.meritnation.com/discuss/question/1983808/0/

  • 0

X = 36 DAYS