Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Number of units | 150 | 180 | 120 | 250 | 160 | 120 | 150 |
For a truck that can carry 2000 cubic feet, hiring cost per day is Rs 1000. Storing cost per cubic feet is Rs 5 per day. If the storage cost is reduced to Rs 0.8 per cubic feet per day, then on which day/days, the truck should be hired?
(A) 4th (B) 7th (C) 4th and 7th (D) None these
This question has not been answered yet!