if 10 workers working for 4 hours complete the work in 12 days how many days will 8 workers work for 6 hours

Dear Student,
Please follow the solution to the above given query:

 As per  the question,
10 workers working for 4 hours a day complete their work = 12 days.
1 person working for 1 hour a day complete the work = 12×10×4 days.
8 workers working for 6 hours a day complete their work =  12×10×48×6=2×102=10 days 
Thus, the 8 persons working for 6 hrs a day complete their work in 10 days.
 
Hope this information will clear your doubts about Unitary Method.

If you have any more doubts just ask here on the forum and our experts will try to help you out as soon as possible.

  • 2
10 workers working for 4 hrs complete the work in 12 days
1   worker   working for 4 hrs complete the work in 12x10 days
So, 8       "               "        "   4 hrs      "          "      "     "   (12x10)/8 days =120/8 days = 15 days
So, 8       "               "        "   1 hr        "          "     "     "       15x4 days
So, 8       "               "        "   6 hrs       "          "     "     "        (15 x 4)/6 days =60 / 6 days =10 days

So, 8 workers working for 6 hrs complete the work in 10 days
                                                                         