IF 11 boys complete a task in 55 days in how many days will 17 boys complete the task working in same rate Share with your friends Share 0 Usaid Fahad answered this 85 0 View Full Answer Usaid Fahad answered this First take out the rate of one boy: 55÷11=5 Then, No. of boys * 5 = 17*5 =85 Hope it is clear!!! 1 Swyam Tyagi answered this 85 1