Pls help experts........ Share with your friends Share 0 Kavita Verma answered this Dear Student, if A can finish a work in 16 days then amount of work done by A in 1 day = 116If B finishes the work in 20 daysthen amount of work done by B in 1 day = 120Amount of work done by both A and B in 1 day = 116 + 120 = 980Amount of work done by both A and B in 8 day = 980 × 8 = 910Amount of work remaining = 1 - 910 = 110amount of work done by B in 1 day = 120amount of work done by B in 2 day = 120×2 = 110 which was thre remaining workSo, B needs 2 more days to finish the work Regards, 0 View Full Answer