2 men can complete the job in 24 days. If the faster one can alone complete the job 20 days faster than the second man, find the time taken by faster man to complete the work.
A) 68 days
B) 40 days
C) 20 days
D) 60 days

Solution 
Let the time taken by slower worker = x days and faster = (x + 20) days
Now, let the rate of slower worker complete the job in = 1xdays
and faster worker complete the job in = 1x+20days
They together complete the work in = 1x+1x+20=x+20+xxx+20=2x+20xx+20days
Therefore, ATQ,
12x+20xx+20=24xx+202x+20=24x2+20x=24(2x+20)x2+20x=48x+480
x- 28x - 480 = 0
x- 40x + 12x - 480 = 0
x(x - 40) + 12(x - 40) = 0
(x - 40)(x + 12) = 0
Either x - 40 = 0 or x + 12 = 0
x = 40 or x = - 12
Neglect the negative term, we get,
x = 40 days = time taken by slower worker
and 
x + 20 = 40 + 20 = 60 days = time taken by faster worker
Hence, D) option is correct. 
 

  • 0
What are you looking for?