Q1 ANS FAST EXPERTS Q1. Raj, Ramesh and Arnav can do a piece of wark in 5 days. If Raj alone do a work in 10 days and Arnav alone can do it in 15 days, in how many days Ramesh can do the work alone ? Share with your friends Share 0 Abhishek Jha answered this Dear Student, Here is the solution of your asked query: Q.1. Raj, Ramesh and Arnav can do a piece of work in 5 days.So their 1 day's work=15Raj can do a work in 10 daysSo, Raj's 1 days work=110Also, Arnav's 1 day's work=115Then, Ramesh's 1 day's work=15-110+115=15-16=130Therefore, total days that Ramesh takes to complete the work = 30 days Regards 1 View Full Answer Muskan Garg answered this 20 0 Hardik Gupta answered this Explain the calculation 0