Q1.
  ​Raj, Ramesh and Arnav can do a piece of wark in 5 days. If Raj alone do a work in 10 days and Arnav alone can do it in 15 days, in how many days Ramesh can do the work alone ? 

Dear Student,
Here is the solution of your asked query:
Q.1. Raj, Ramesh and Arnav can do a piece of work in 5 days.So their 1 day's work=15Raj can do a work in 10 daysSo, Raj's 1 days work=110Also, Arnav's 1 day's work=115Then, Ramesh's 1 day's work=15-110+115=15-16=130Therefore, total days that Ramesh takes to complete the work = 30 days