Solve this :

A machine is used to lift a load of 20 N through a height of 10 m. If the efficiency of the machine is 40% how much work is done ?

Dear Student,
                      Work done =20×10=200Jas efficiency is 40%then total work done by machine =200×100/40=500J
Regards